Having received concerns from residents in my mailbox surrounding the odour in the Hythe area, I contacted Anglian Water to ask what action they are taking on their site on the quay to minimise the odour. I have been provided with an update from Anglian Water on their new odour control unit and I am pleased to confirm the following:
👉 Funding for their new odour control unit work has now been approved.
👉 A design handover meeting with the Anglian Water IOS team was held on 2 November and a site meeting was held with their supplier and designer on 19 November.
👉 The additional proposed works that include a new import tank roof on their site and modifications to the imported cake building have also received approval, and a Peer review was arranged with their construction team on 12 November to progress into the construction phase.
I am being provided with a further update soon, and I will continue to keep residents informed.